Deugro/Linde

Image 1

The top part of the C3 splitter is being loaded on the tank top of the MV “Beluga Intonation”.


Image 2

Under the surveillance by the team of Beluga: The loading of the bottom part of the C3 splitter.


Image 3

Just a few months ago, the MV “Beluga Intonation” has been cut in the middle, lengthened and provided with stronger board cranes.


Image 4

The board cranes of the multipurpose heavy-lift project carrier are lifting the bottom part of the C3-splitter onto the weather deck. The unit weighs 340 tons and is 63 meters long.


Image 5

On the pier ready for loading: The Demethanizer, measuring 66 meters and weighing 340 tons.


 

print | recommend 
http://www.beluga-group.com/en/references/oil-gas/deugrolinde/pictures/
en
| RSS-Feed
 
content.html